Timeline 2020-21
1st Year Overall F, 1st Year Comprehensive Identified, Campus with 1882 Partnership Identified Overall F or Comprehensive
All: Option 1 & 2
Option 1 – Not Delayed
Option 2 – Delayed
August & September 2020
Campus attends Targeted Improvement Plan (TIP) Training
August 31st
Superintendent uploads DCSI name in ISAM
DCSI Submits RPA in ISAM
October 5th
DCSI Attends Survey Coordinator Training with Panorama
October 9th
DCSI submits TIP (Attestation Statement, Foundations, Student Data, and Cycles 1 – 3 tabs) in ISAM
October 12th
Diagnostic Survey Window Opens (Panorama)
October 23rd
DCSI submits Campus Allocation Document for School Improvement Grant, only if the campus is also rated comprehensive
October & November
ESF Facilitators begin reaching out to campuses to assign pre-work and schedule visits.
- Calls happen 2 months before campus visit
- Campus will have 4 weeks to complete and return pre-work
- Facilitators will conduct a pre-visit phone call
DCSI presents TIP to School Board for approval
TEA calls DSCI for initial TIP feedback
November 20th
Diagnostic Survey Window Closes (Panorama)
December 7th
Diagnostic Survey Data released to Schools (Panorama)
December 14th
Panorama Data Review Webinar for DCSI and Principal
December 18th
TIP Progress #1 submission due in ISAM. Artifacts are included in this submission
DCSI submits TIP (Attestation Statement, Foundations, Student Data, and Cycles 2 – 3 tabs) in ISAM
January & February
TEA will hold phone conference to discuss Progress #1 Submission
TEA will hold phone conference to discuss RPA and Initial TIP Submission
January 18th
Spring 2021 Spring Diagnostic Visit Window Opens
- Facilitator conducts campus visit
- Facilitator will meet for post-visit within 1 week after initial campus visit
- Facilitator will submit final report to ISAM within 2 weeks of initial campus visit
January 29th
ESF Facilitator Name due in ISAM
March 5th
TIP Progress #2 Submission due in ISAM. Artifacts are included in this submission
DCSI submits Comprehensive Funding report in ISAM.
April 30th
Spring 2021 Spring Diagnostic Visit Window Closes
June 4th
TIP Progress #3 submission due in ISAM. Artifacts are included with this submission.